|
1
|
|
|
2
|
- ENR Upgrade and Expansion of the Region II Wastewater Treatment Plant
- Gravity Sewer Collection System Improvements in the St. Michaels Area
- Separate Environmental Project – Establishment of decentralized
sanctuaries for aquatic species
- Pilot of the On-Site Sewage Disposal System Management Strategy
- Issues to consider – open discussion
|
|
3
|
- Improve the Water Quality of the effluent being discharged from the
Region II Wastewater Treatment Plant; and
- Eliminate sanitary sewer overflows and surcharging conditions of the
gravity sewer system; and
- Reduce extraneous flows, typically referred to as Inflow and
Infiltration (I&I) entering the gravity sewer system.
|
|
4
|
- Constructed in early 1950s (As-built - 1954)
- 34,000+ lineal feet of 8, 10, 12 and 15 inch diameter pipes
- Pipe materials include
- Vitrified Clay Pipe – 5 foot pipe sections
- PVC pipe – 20 foot pipe sections
- Possibly some HDPE Pipe
- Over 225 manholes (MHs)
- Materials of Construction
- Average depth - 7 vertical feet
- Internal diameter (ID) typically – 4 feet
|
|
5
|
|
|
6
|
|
|
7
|
- Inflow and Infiltration (I & I) Corrective Action
- August 2001 - County Council approved in-pipe flow monitoring contract
with Maryland Environmental Service (MES)
- November/December 2001 - Department of Public Works (DPW) delayed flow
monitoring investigation due to drought conditions
- December 2002 - MES initiated in-pipe flow monitoring
- March 2003 - MES conducted preliminary sewer collection system
inspections
- April 2003 - County Council approved expanded scope of work for sewer
collection system investigation that includes smoke testing
- February 2004 submitted grant applications to repair collection system
- July 2005 – MDE awards Talbot County $500,000 in grant funds for the
pump station improvements
- August 2005 – Talbot County initiates sewer replacement designs for
Mill and Carpenter Streets
- November 2005 - Bids received for the Pump Station Improvements and
Force Main Construction projects and initiated Manhole Inspections
- March 2006 – MDE approves an additional $500,000 in grant funds for the
force main construction
- April 2006 – Notice to proceed issued to contractors for Pump Station
Upgrades and new Force Main and County seeks approval for $593,590 for
sewer line improvements from MDE and County Council
|
|
8
|
|
|
9
|
|
|
10
|
- Allocated ENR/BNR Grant Funding: $
4,718,578
- SRF Loan Amount: $ 8,317,699
- Total Design and Construction Cost: $ 13,036,277
- Pump Station Upgrades:
- Grant Funding: $ 500,000
- State Revolving Funds for Loans: $1,183,732
- Force Main:
- Grant Funding: $ 500,000
- State Revolving Funds for Loans: $
810,450
- Community of Rio Vista and Sections of St. Michaels Gravity Sewer
Collection System Cleaning, TV Inspection, Joint Testing and Pressure
Grouting – Sanitary District Funds
- Total Cost (Complete by February, 2006): $ 229,178
- Manhole Rehabilitation and Slip Lining: $ 650,000
- Sewer Replacements: $ 2,000,000
- Additional Slip Lining: $
750,000
- TOTAL COSTS: $19,658,637
|