10
Region II Wastewater Treatment Plant Costs
•
–Allocated ENR/BNR Grant Funding: $  4,718,578
–SRF Loan Amount: $  8,317,699
–Total Design and Construction Cost: $ 13,036,277
–
–Pump Station Upgrades:
•Grant Funding: $   500,000
•State Revolving Funds for Loans: $1,183,732
–Force Main:
•Grant Funding: $    500,000
•State Revolving Funds for Loans: $    810,450
–Community of Rio Vista and Sections of St. Michaels Gravity Sewer Collection System Cleaning, TV Inspection, Joint Testing and Pressure Grouting – Sanitary District Funds
•Total Cost (Complete by February, 2006): $   229,178
–Manhole Rehabilitation and Slip Lining: $   650,000
–Sewer Replacements: $ 2,000,000
–Additional Slip Lining: $   750,000
–
–TOTAL COSTS: $19,658,637
–